Ineos Group Ltd.’s €4 billion Project One ethane cracker investment at Antwerp, Belgium is moving ahead after a delay caused by the suspension of the cracker’s environmental permit following a campaign by environmentalists over the alleged impact of nitrogen emissions.
“Since Ineos regained a permit for Project One in early January 2024, after it got annulled in July 2023, works on the construction site in Antwerp have been in full swing after a five-month standstill,” John McNally, CEO of Project One, told CW in an interview ahead of the European Petrochemical Association (EPCA) Annual Meeting, which takes place in Berlin Oct. 7-10. McNally is also an EPCA board member.
“At this stage, we have surpassed the mark of 1,300 people working simultaneously on our site in Antwerp,” McNally said. “In the first half of this year the focus was on underground and civil engineering works such as foundation works, concrete pouring, laying underground pipes, roads, substations and utilities.”
One key piece of infrastructure has been erected since May — the ethane tank, which McNally calls “the logistics heart of Project One.” With a capacity of 197,000 cubic meters, it is the largest cryogenic tank in Europe, he said.
“After the summer, the site will go really vertical, when the shipped modules will come in, which have been built in multiple overseas yards,” McNally said. “These works have not been impacted by the permit annulment in Antwerp.” The modules include pipe racks, cracking furnaces and process units weighing up to 10,000 metric tons. “At our nearby Lillo site, we are getting everything ready for the reception and construction of these modules,” he added. “The quay wall and the offloading platform, for example, have now been finalized.”
Ineos still aims to go live with the 1.45 million metric tons per year ethylene plant at the end of 2026, McNally said.
But the permitting difficulties have made it “a very challenging journey” since Ineos announced the Project One investment in January 2019 — the first new cracker to be built in Europe for 25 years — McNally said. “We have written a permit application totalling 5,176 pages to get to build Project One,” he said. “When our permit was annulled, it took six months and another 832 pages to recover the permit, in the form of detailed environmental research to demonstrate that our negligible deposition of nitrogen does not have a significant impact on nature reserves. We are now five years later and naturally our permit and legal team is making every effort to ensure maximum legal certainty for the project.”
In July 2024, the Flemish Minister of Environment withdrew the January decision to restore the original permit and issued a new environmental permit for Project One. The new permit also refers to Flanders’ Nitrogen Decree, providing for limits on nitrogen emissions, which came into force at the end of February. “This way legal certainty is increased,” McNally said. “For megaprojects like ours it is extremely difficult to be exposed to this kind of legal uncertainty.”
mrchub.com